Project Timeline

..............................................................................................................

September 2014

Environmental Impact Assessment started

..............................................................................................................

September 2015

Submission of Scoping Report to The Scottish Government 

..............................................................................................................

Winter 2015 and Spring 2016

Public consultation in the form of two public exhibitions undertaken

..............................................................................................................

Autumn 2016

Submitted Section 36 Application for consent to the Scottish Government

..............................................................................................................

June 2019

Section 36 Application refused

..............................................................................................................

Autumn 2019

Public consultation in the form of one public exhibition undertaken

..............................................................................................................

Winter 2019/20

Submitted Application for Planning Permission to Highland Council

..............................................................................................................

Winter 2021/22

Decision on Application for Planning Permission anticipated